Week of 12/26/16 - first visit to the community, quote, and decision

01/02/17 - signed purchase agreement
01/06/17 - meeting with Patti, loan officer, for loan application
01/07/17 - meeting with Guardian to discuss technology package
01/13/17 - first email contact with Bryson, loan processor
01/16/17 - loan application submitted to the underwriting team for approval
01/18/17 - loan approved
02/07/17 - pre-construction meeting
02/08/17 - breaking ground
Week of 02/13 - foundation completed
Week of 03/06 - framing completed (lumber and roof)
Week of 03/20 - shingles installed, HVAC completed, and plumbing rough-ins done. Dormers NOT installed - issue pending
04/03/17 - appraisal complete
04/04/17 - pre-drywall meeting
05/09/17 - loan final approval
05/30/17 - final walkthrough
06/02/17 - settlement date




(This timeline will be updated as the process unfolds)